Chashma 4 (Chasnupp-4), Pakistan
| CURRENT STATUS |
| Under Construction |
|
| Process | PWR |
| Owner | Pakistan Atomic Energy Commission |
| Model | CNP-300 |
| Operator | Pakistan Atomic Energy Commission |
| Capacity Net | 315 MWe |
| Capacity Gross | 340 MWe |
| Capacity Thermal | 999 MWt |
| |
|
| Start Construction | 18 December 2011 |
| Criticality | 1 June 2017 |
| Grid Connection | 1 July 2017 |
| Commercial Operation | 1 October 2017 |
| |
|