Karachi-1 (Kanupp-1), Pakistan
|
| Reactor Type | Commercial Reactor |
| Process | PHWR |
| Vendor | CGE |
| Owner | Pakistan Atomic Energy Commission |
| Model | CANDU-137 MW |
| Operator | Pakistan Atomic Energy Commission |
| Capacity Net | 125 MWe |
| Capacity Gross | 137 MWe |
| Capacity Thermal | 433 MWt |
| |
|
| Start Construction | 1 August 1966 |
| Criticality | 1 August 1971 |
| Grid Connection | 18 October 1971 |
| Commercial Operation | 7 December 1972 |
| |
|
| Output Life | 12.47 TWh |
| Capacity Factor Life | 28.3 % |