Seabrook-1, United States
|
| Reactor Type | Commercial Reactor |
| Process | PWR |
| Vendor | Westinghouse |
| Owner | Nextera Energy Resources, Llc |
| Model | W (4-loop) DRYAMB |
| Operator | Nextera Energy Resources, Llc |
| Capacity Net | 1246 MWe |
| Capacity Gross | 1296 MWe |
| Capacity Thermal | 3648 MWt |
| |
|
| Start Construction | 7 July 1976 |
| Criticality | 13 June 1989 |
| Grid Connection | 29 May 1990 |
| Commercial Operation | 19 August 1990 |
| |
|
| Output Life | 197.87 TWh |
| Capacity Factor Life | 84.9 % |