Heysham-A2, United Kingdom
|
| Reactor Type | Commercial Reactor |
| Process | GCR |
| Vendor | National Nuclear Corp (NNC) |
| Owner | Edf Energy |
| Model | AGR |
| Operator | Edf Energy |
| Capacity Net | 575 MWe |
| Capacity Gross | 625 MWe |
| Capacity Thermal | 1500 MWt |
| |
|
| Start Construction | 1 December 1970 |
| Criticality | 3 June 1984 |
| Grid Connection | 11 October 1984 |
| Commercial Operation | 1 April 1989 |
| |
|
| Output Life | 79.48 TWh |
| Capacity Factor Life | 66.4 % |