Rheinsberg KKR, Germany

Overview
CURRENT STATUS
Permanent Shutdown
DETAILS
Reactor TypeCommercial Reactor
ProcessPWR
VendorAtomenergoexport
OwnerEnergiewerke Nord Gmbh
ModelVVER-70
OperatorEnergiewerke Nord Gmbh
Capacity Net62 MWe
Capacity Gross70 MWe
Capacity Thermal265 MWt
 
CONSTRUCTION AND OPERATION
Start Construction1 January 1960
Criticality1 March 1966
Grid Connection6 May 1966
Commercial Operation11 October 1966
Shutdown1 June 1990
 
OPERATING PERFORMANCE
 

 
 


Reactor Operational Details

YearReference Unit Power MWAnnual Output GWhAnnual Time On Line HoursCapacity Factor %Operational Factor %
197300000
197400000
197500000
197600000
197700000
197800000
197900000
198000000
198100000
198200000
198300000
198400000
198500000
198600000
198700000
198800000
198900000
Total:

Source: Operating details - IAEA PRIS
Note: "0" signifies a zero value, or no data available. Data from 1972 or later. 