Hinkley Point-A1, United Kingdom
| CURRENT STATUS |
| Permanent Shutdown |
|
| Reactor Type | Commercial Reactor |
| Process | GCR |
| Vendor | EE/BW/TW |
| Owner | Nuclear Decommissioning Authority |
| Model | MAGNOX |
| Operator | Magnox Electric Limited |
| Capacity Net | 235 MWe |
| Capacity Gross | 267 MWe |
| Capacity Thermal | 900 MWt |
| |
|
| Start Construction | 1 November 1957 |
| Criticality | 1 May 1964 |
| Grid Connection | 16 February 1965 |
| Commercial Operation | 30 March 1965 |
| Shutdown | 23 May 2000 |
| |
|
| Output Life | 46.47 TWh |
| Capacity Factor Life | 72.4 % |