Berkeley-1, United Kingdom
| CURRENT STATUS |
| Permanent Shutdown |
|
| Reactor Type | Commercial Reactor |
| Process | GCR |
| Vendor | The Nuclear Power Group (TNPG) |
| Owner | Nuclear Decommissioning Authority |
| Model | MAGNOX |
| Operator | Magnox Electric Limited |
| Capacity Net | 138 MWe |
| Capacity Gross | 166 MWe |
| Capacity Thermal | 620 MWt |
| |
|
| Start Construction | 1 January 1957 |
| Criticality | 1 August 1961 |
| Grid Connection | 12 June 1962 |
| Commercial Operation | 12 June 1962 |
| Shutdown | 31 March 1989 |
| |
|
| Output Life | 21.01 TWh |
| Capacity Factor Life | 58.2 % |