| Reactor Type | Commercial Reactor |
| Process | PWR |
| Vendor | Westinghouse |
| Owner | Iberdrola, Endesa, Gas Natural |
| Model | WE 3-loops |
| Operator | Centrales NuclearesAlmaraz-Trillo(Id/Ufg/Endesa/Hc/Nuclenor ) |
| Capacity Net | 1004 MWe |
| Capacity Gross | 1049 MWe |
| Capacity Thermal | 2947 MWt |
| |
|
| Start Construction | 3 July 1973 |
| Criticality | 5 April 1981 |
| Grid Connection | 1 May 1981 |
| Commercial Operation | 1 September 1983 |
| |
|
| Output Life | 209.5 TWh |
| Capacity Factor Life | 85.6 % |
| WNN Link | Uprates for Almaraz units |
| Net Capacity (WNA) | 1050 MWe |