Wolsong-2, Korea RO (South)
|
| Reactor Type | Commercial Reactor |
| Process | PHWR |
| Vendor | Atomic Energy of Canada Ltd (AECL)/Hanjung |
| Owner | Korea Hydro And Nuclear Power Co. |
| Model | CANDU 6 |
| Operator | Korea Hydro And Nuclear Power Co. |
| Capacity Net | 673 MWe |
| Capacity Gross | 698 MWe |
| Capacity Thermal | 2061 MWt |
| |
|
| Start Construction | 22 June 1992 |
| Criticality | 29 January 1997 |
| Grid Connection | 1 April 1997 |
| Commercial Operation | 1 July 1997 |
| |
|
| Output Life | 87.77 TWh |
| Capacity Factor Life | 94.5 % |