Heysham-B2, United Kingdom
|
| Reactor Type | Commercial Reactor |
| Process | GCR |
| Vendor | Nuclear Power Corp (NPC) |
| Owner | Edf Energy |
| Model | AGR |
| Operator | Edf Energy |
| Capacity Net | 610 MWe |
| Capacity Gross | 680 MWe |
| Capacity Thermal | 1550 MWt |
| |
|
| Start Construction | 1 August 1980 |
| Criticality | 1 November 1988 |
| Grid Connection | 11 November 1988 |
| Commercial Operation | 1 April 1989 |
| |
|
| Output Life | 93.07 TWh |
| Capacity Factor Life | 74.1 % |