Winfrith SGHWR, United Kingdom
| CURRENT STATUS |
| Permanent Shutdown |
|
| Process | SGHWR |
| Owner | United Kingdom Atomic Energy Authority |
| Operator | United Kingdom Atomic Energy Authority |
| Capacity Net | 92 MWe |
| Capacity Gross | 100 MWe |
| Capacity Thermal | 318 MWt |
| |
|
| Start Construction | 1 May 1963 |
| Criticality | 1 September 1967 |
| Grid Connection | 1 December 1967 |
| Commercial Operation | 1 January 1968 |
| Shutdown | 11 September 1990 |
| |
|
| Output Life | 10.96 TWh |
| Capacity Factor Life | 60.7 % |