Douglas Point (Prototype), Canada
| CURRENT STATUS |
| Permanent Shutdown |
|
| Reactor Type | Commercial Reactor |
| Process | PHWR |
| Vendor | Atomic Energy of Canada Ltd (AECL) |
| Owner | Atomic Energy Of Canada Ltd. |
| Model | CANDU 200 |
| Operator | Ontario Hydro |
| Capacity Net | 206 MWe |
| Capacity Gross | 218 MWe |
| Capacity Thermal | 704 MWt |
| |
|
| Start Construction | 1 February 1960 |
| Criticality | 15 November 1966 |
| Grid Connection | 7 January 1967 |
| Commercial Operation | 26 September 1968 |
| Shutdown | 4 May 1984 |
| |
|
| Output Life | 15.63 TWh |
| Capacity Factor Life | 55.6 % |