Fugen ATR, Japan

Overview
CURRENT STATUS
Permanent Shutdown
DETAILS
Reactor TypeCommercial Reactor
ProcessHWLWR
VendorHitachi
OwnerJapan Atomic Energy Agency
ModelATR
OperatorJapan Atomic Energy Agency
Capacity Net148 MWe
Capacity Gross165 MWe
Capacity Thermal557 MWt
 
CONSTRUCTION AND OPERATION
Start Construction10 May 1972
Criticality20 March 1978
Grid Connection29 July 1978
Commercial Operation20 March 1979
Shutdown29 March 2003
 
OPERATING PERFORMANCE
Output Life8.45 TWh
Capacity Factor Life61.9 %
 

 
 


Reactor Operational Details

YearReference Unit Power MWAnnual Output GWhAnnual Time On Line HoursCapacity Factor %Operational Factor %
1978148144.33179300
19791501009.6732283.387.7
1980148630.7452348.551.5
1981148242.8184018.721
1982148819.22570663.265.1
19831481106772485.388.2
1984148767.0555025962.6
1985148670.69466151.753.2
19861481034.42722179.882.4
1987148725.6850555657.7
19881481015.42697678.179.4
1989148809.09565662.464.6
19901481081.1752683.485.9
1991148671.28472851.854
1992148933.87639771.872.8
1993148857.25591566.167.5
19941481182.83804091.291.8
1995148797.03549161.562.7
1996148991.23675176.276.9
1997148520.81365640.241.7
19981481186.37808591.592.3
1999148445.44280631.432
2000148569.3396443.845.1
2001148507.46343039.139.2
2002148606.28452846.851.7
Total:19325.25

Source: Operating details - IAEA PRIS
Note: "0" signifies a zero value, or no data available. Data from 1972 or later. 