Share

WNN Latest news

Nuclear Power in Belarus

(Updated 30 June 2014)

  • Belarus has its first nuclear power plant under construction and plans to have it operating from operating from 2018, with Russian finance. 
  • Atomstroyexport is building the 2400 MWe plant, with two reactors.

Belarus produces only 32 billion kWh/yr from 8 GWe of plant, mostly gas-fired, giving per capita consumption of 3330 kWh/yr. Government plans to reform the electricity sector by creating a wholesale market in three stages have stalled, and electricity remains heavily subsidised for households.

Under its 2011-2020 energy strategy, Belarus is seeking to reduce its reliance on Russia as a major energy supplier. The plan calls for a 1000 MWe coal-fired plant and a 2400 MWe nuclear power plant as well as four hydropower stations with total capacity of 120 MW, and wind projects totaling 300 MW. If fully implemented, the strategy would bring the share of power generated using Russian gas down to 55% by 2020, from over 80% in 2009. Gas demand should decrease by one-third.

The country imports 90% of its gas from Russia (estimate of 22.5 billion m3 in 2012) – much of it for electricity – and overall aims for 25-30% energy independence, compared with half that now. The proposed 2400 MWe nuclear plant is expected to reduce gas imports by 5 billion m3 per year, now costing over US$ 800 million, while the fuel and waste management for it would be a quarter of this. In November 2011 it was agreed that Russia's Gazprom would pay $2.5 billion for the 50% of Belarus' gas transmission network, Beltransgaz, that it did not already own. This was linked both to lower gas prices and to Russian finance for the nuclear plant. Earlier, there had been studies on both a domestic nuclear power plant using Russian technology, and Belarus participation in a new nuclear unit at Smolensk or Kursk in Russia. 

Plans for nuclear capacity 

In mid 2006 the government approved a plan for the construction of an initial 2000 MWe PWR nuclear power plant in the in the Mogilev region of eastern Belarus. This was expected to provide electricity at half the cost of that from Russian gas (5 billion cubic metres per year for same capacity) and to provide some 30% of the electricity by 2020 at a cost of about €4 billion (January 2008 estimate) on a turnkey basis.

After expressions of interest from international reactor vendors were invited, the energy ministry announced in August 2008 that proposals had been received from Atomstroyexport, Westinghouse-Toshiba and Areva. Anything from USA would need several years for an intergovernmental agreement, and Areva's EPR was noted as being too big for the first plant. In addition, the energy ministry received a proposal from the China Guangdong Nuclear Power Corporation. Russia's Atomstroyexport emerged as the most likely supplier for the 2 x 1000 MWe plant since the others either did not provide all the information required or could not build the plant soon enough. Operation of the first unit was envisaged for 2016 and the second in 2018. Two further units are proposed for operation by 2025. In June 2007 Russia's Eximbank offered a US$ 2 billion credit line to enable purchase of equipment from Russia's Power Machines company as a major part of the overall cost.

In November 2007 a presidential decree defined the organizations responsible for preparing for the construction of the country's first nuclear power plant and budgeted money for engineering and site selection. The candidate sites were Krasnopolyansk and Kukshinovsk (both in the Mogilev region) and Ostrovets in the Grodno region. Ostrovets/ Astravets, 23 km from the Lithuanian border and 55 km from Vilnius, was chosen in December 2008, despite protests from Lithuania. Ownership of the plant could be partly or wholly private, and the Bulgarian precedent was being watched with interest (or despair).

The decree also aims to ensure that nuclear and radiation safety is in line with the recommendations of the International Atomic Energy Agency (IAEA). A Directorate for Construction of Nuclear Power Plants was established under the Ministry of Energy. A Nuclear & Radiation Safety Department will also be set up as part of the Emergencies Ministry to act as the state nuclear regulator and licensing authority. The state-run Belnipienergoprom enterprise was designated as the general designer of the plant and will be responsible for negotiating and signing contracts, carrying out feasibility studies and preparing tender documents.

In June 2009 the government announced that Atomstroyexport would be the general contractor, with Russian and Belarus subcontractors, notably St Petersburg Atomenergoproekt. An intergovernmental agreement concerning the plant was signed in March 2011. A preliminary turnkey construction contract with Atomstroyexport for a 2400 MWe plant (2 x 1200 MWe AES-2006 units using V-491 reactors) was signed in October 2011 by Belarus state-owned Nuclear Power Plant Construction Directorate, and a general construction contract was signed in July 2012. St Petersburg AEP (SPbAEP, now VNIPIET) has been involved with the project since 2004, including site selection and technology choice. In January 2014 the Nuclear Power Plant Construction Directorate became the Belarus Nuclear Power Plant state unitary enterprise.

Operation of the first unit of the Ostrovets plant is scheduled for November 2018 and the second unit in July 2020, to give 2340 MWe net on line. 

 In December 2011 the Nuclear Power Engineering Department of the Energy Ministry submitted an application for a construction license to state nuclear regulator Gosatomnadzor (GAN). During 2012 some site works were under way, and excavation for the second unit started in February 2013. Construction of the first unit started in November 2013 with first structural concrete, though the full construction licence was not issued until April 2014. A construction licence for the base mat of unit 2 was issued by the Ministry in February 2014. Construction of unit 2 started in May 2014, several months ahead of schedule.

Planned Belarus Nuclear Power Reactors

  Reactor MWe gross

Start construction

Commercial operation
Ostrovets 1 VVER-1200/491 1200 Nov 2013 Early 2019
Ostrovets 2 VVER-1200/491 1200 May 2014 Late 2020

Two further units are proposed for about five years later. 

In June 2009 the government announced that US$ 9 billion Russian financing had been lined up, and Belarus also wanted the Russian loan to include provision for infrastructure. Belarus official cost estimate including infrastructure was US$ 9.4 billion, with one third of this to be spent 2011-15. In November 2011 it was agreed that Russia would lend up to $10 billion for 25 years to finance 90% of the contract between Atomstroyexport and the Belarus Directorate for Nuclear Power Plant Construction (now the Belarus NPP state unitary enterprise). In February 2012 Russian state-owned Vnesheconombank (VEB) and Belarusian commercial bank Belvnesheconombank (BelVEB) signed an agreement needed to implement the Russian export credit facility. In May 2012 the parties said that the first instalment under the design contract would be $204 million, and that this would be followed by $285 million for pre-construction site works. This was confirmed with an agreement signed in May 2014.

In April 2013 Atomenergomash (AEM) won the tender to supply the two reactors, which will be manufactured by AEM-Technologies at the Atommash plant at Volgodonsk. The Department for Nuclear and Radiation Safety (Gosatomnadzor) of the Ministry of Emergencies issued the State Entity Nuclear Power Plant Construction Directorate (Belarus AEC) with a licence for the construction of the first reactor at the Ostrovets site in October. First concrete was in November 2013, with VNIPIET (formerly SPbAEP) as main contractor. The construction time for the first unit is expected to be 60 months, with grid connection of the unit due in November 2018. The timetable for the second unit was to be about 18 months behind it, with commissioning set for July 2020, but in the event there was only a six-month gap.

Belarus used INPRO’s Nuclear Energy Systems Assessment methodology covering economics, infrastructure, waste management, proliferation resistance, physical protection, environment, and safety to confirm its investment decision. The results showed that nuclear would be competitive, with overnight costs US$1960/kW and levelized electricity price 5.81 cent/kWh (compared with coal $1175/kW and 6.52 cent/kWh, and gas $805/kW and 6.76 cent/kWh). The basic overnight cost of the two units was put at $6.135 billion.

Russia's policy for building nuclear power plants in non-nuclear weapons states is to deliver on a turnkey basis, including supply of all fuel and repatriation of used fuel for the life of the plant. The fuel is to be reprocessed in Russia and the separated wastes returned to the client country eventually.

In May 2009 the government approved a nuclear cooperation agreement with China, which includes nuclear power, joint development of innovative reactor technologies, nuclear safety, radiation protection and environmental protection as well as radiation technologies and their applications, nuclear medicine and radiation therapy. It creates a legal basis for Chinese participation in nuclear power plant and related construction in Belarus. It follows both a 2008 proposal from China Guangdong Nuclear Power Group (CGNPC) and a 2005 cooperation agreement. Early in 2010 official announcements said that the President had proposed to cooperate with China in nuclear power, including the construction of a power plant, although Chinese official sources did not confirm this. In July 2012 the North China Power Engineering Co Ltd (NCPE) won a contract from Grodnoenergo to build a 330 kV transmission line to connect Ostrovets power plant to the grid. This would be financed by China Exim Bank.

In August 2102 the government said that there were no specific plans for a second nuclear power plant but the question remained on the agenda. A decision on it will be made once the first is operational, and in the light of costs and energy options then.

A VVER-1000 unit was earlier being built near Minsk but construction was abandoned in 1988 after the Chernobyl accident.

Public Opinion

Public opinion monitoring conducted by the Ministry of Energy jointly with the National Academy of Sciences shows a sustainable growth of support to nuclear power over the period September 2005 to May 2012. The number of nuclear power supporters increased from 28.3% to 53.5% over that period, while the number of opponents decreased from 46.7% to 21%. Slight fluctuations were observed in 2012 after the accident at Fukushima-Daiichi, which triggered “a new outburst of anxiety.” An important result of the studies is the fact that they “unambiguously recorded” positive shifts in public attitude to “calm and reasoned perception”, despite the fact that Belarus was very affected by fallout from the Chernobyl accident, with resultant evacuations.

Non-proliferation 

Belarus joined the NPT in 1995, and in 2005 signed the additional protocol to its safeguards agreement with IAEA.