Details

Reactor Type Pressurised Water Reactor (or PWR)
Model VVER V-491
Owner Joint Stock Company 'Concern Rosenergoatom'
Operator Joint Stock Company 'Concern Rosenergoatom'

Timeline

Construction Start Thursday, 15 April 2010
First Criticality Saturday, 29 August 2020
First Grid Connection Thursday, 22 October 2020
Commercial Operation Monday, 22 March 2021

Specifications

Capacity Net 1101 MWe
Capacity Gross 1188 MWe
Thermal Capacity 3200 MWt
Design Net Capacity 1066 MWe

Operational History

Electricity Supplied (GWh)

Energy Availability Factor (%)

Total Electricity Supplied (GWh)

Reactor History

Year Reference Unit Power (MWe) Annual Time Online (Hours) Electricity Supplied (GWh) Operation Factor (%) Energy Availability Annual (%) Energy Availability Cumulative (%) Load Factor Annual (%) Load Factor Cumulative (%)
2020 1066 1242 659.54 - - - - -
2021 1101 7935 8361.90 91.70 88.40 88.40 88.90 88.90
2022 1101 6919 7510.31 79.00 77.60 82.30 77.90 82.60
2023 1101 7905 8555.51 90.20 88.30 84.50 88.70 84.80

Source: Operating details - IAEA PRIS