Details

Reactor Type Pressurised Water Reactor (or PWR)
Model APR-1400
Owner Emirates Nuclear Energy Corporation
Operator Nawah Energy Company

Timeline

Construction Start Thursday, 30 July 2015
First Criticality Friday, 1 March 2024
First Grid Connection Saturday, 23 March 2024
Commercial Operation Thursday, 5 September 2024

Specifications

Capacity Net 1337 MWe
Capacity Gross 1417 MWe
Thermal Capacity 3983 MWt
Design Net Capacity 1310 MWe