Details

Reactor Type Pressurised Water Reactor (or PWR)
Model VVER V-320
Owner Joint Stock Company 'Concern Rosenergoatom'
Operator Joint Stock Company 'Concern Rosenergoatom'

Timeline

Construction Start Wednesday, 16 June 2010
First Criticality Friday, 29 December 2017
First Grid Connection Friday, 2 February 2018
Commercial Operation Friday, 28 September 2018

Specifications

Capacity Net 979 MWe
Capacity Gross 1030 MWe
Thermal Capacity 3000 MWt
Design Net Capacity 950 MWe

Operational History

Electricity Supplied (GWh)

Energy Availability Factor (%)

Total Electricity Supplied (GWh)

Reactor History

Year Reference Unit Power (MWe) Annual Time Online (Hours) Electricity Supplied (GWh) Operation Factor (%) Energy Availability Annual (%) Energy Availability Cumulative (%) Load Factor Annual (%) Load Factor Cumulative (%)
2018 950 6556 5681.92 100.00 100.00 100.00 103.80 103.80
2019 979 7751 7430.57 88.50 87.00 89.60 86.60 90.00
2020 979 8573 8066.50 97.60 94.90 91.90 93.80 91.70
2021 979 7862 7521.96 89.80 88.00 90.70 87.70 90.50
2022 979 7761 7542.06 88.60 87.30 89.90 87.90 89.90
2023 979 8760 8450.68 100.00 97.90 91.40 98.50 91.50

Source: Operating details - IAEA PRIS


See Also

Nuclear Power in Russia

Related News

WNN articles on Russia
Subscribe to receive updates on news