Details
Reactor Type | Pressurised Water Reactor (or PWR) |
---|---|
Model | APR-1400 |
Owner | Emirates Nuclear Energy Corporation |
Operator | Nawah Energy Company |
Timeline
Construction Start | Wednesday, 24 September 2014 |
---|---|
First Criticality | Thursday, 22 September 2022 |
First Grid Connection | Saturday, 8 October 2022 |
Commercial Operation | Friday, 24 February 2023 |
Specifications
Capacity Net | 1337 MWe |
---|---|
Capacity Gross | 1417 MWe |
Thermal Capacity | 3983 MWt |
Design Net Capacity | 1310 MWe |
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Operational History
Electricity Supplied (GWh)
Energy Availability Factor (%)
Total Electricity Supplied (GWh)
Reactor History
Year | Reference Unit Power (MWe) | Annual Time Online (Hours) | Electricity Supplied (GWh) | Operation Factor (%) | Energy Availability Annual (%) | Energy Availability Cumulative (%) | Load Factor Annual (%) | Load Factor Cumulative (%) |
---|---|---|---|---|---|---|---|---|
2022 | 1337 | 1703 | 1189.53 | - | - | - | - | - |
2023 | 1337 | 7865 | 10442.83 | 97.70 | 96.80 | 96.80 | 97.70 | 97.70 |