| Reactor Type | Light Water Graphite Reactor (or LWGR) |
|---|---|
| Model | AMB-100 |
| Owner | Ministry Of Medium Machine Building Of The Ussr (Minsredmash) |
| Operator | Joint Stock Company 'Concern Rosenergoatom' |
Timeline
| Construction Start | Sunday, 1 June 1958 |
|---|---|
| First Criticality | Sunday, 1 September 1963 |
| First Grid Connection | Sunday, 26 April 1964 |
| Commercial Operation | Sunday, 26 April 1964 |
| Permanent Shutdown | Saturday, 1 January 1983 |
Specifications
| Capacity Net | 102 MWe |
|---|---|
| Capacity Gross | 108 MWe |
| Thermal Capacity | 286 MWt |
| Design Net Capacity | 102 MWe |
Operational History
Electricity Supplied (GWh)
Energy Availability Factor (%)
Total Electricity Supplied (GWh)
Reactor History
| Year | Reference Unit Power (MWe) | Annual Time Online (Hours) | Electricity Supplied (GWh) | Operation Factor (%) | Energy Availability Annual (%) | Energy Availability Cumulative (%) | Load Factor Annual (%) | Load Factor Cumulative (%) |
|---|---|---|---|---|---|---|---|---|
| 1964 | - | - | - | - | - | - | - | - |
| 1965 | 102 | 0 | 0.00 | - | - | - | - | - |
| 1966 | 102 | 0 | 0.00 | - | - | - | - | - |
| 1967 | 102 | 0 | 0.00 | - | - | - | - | - |
| 1968 | 102 | 0 | 0.00 | - | - | - | - | - |
| 1969 | - | - | - | - | - | - | - | - |
| 1970 | - | - | - | - | - | - | - | - |
| 1971 | - | - | - | - | - | - | - | - |
| 1972 | - | - | - | - | - | - | - | - |
| 1973 | - | - | - | - | - | - | - | - |
| 1974 | - | - | - | - | - | - | - | - |
| 1975 | - | - | - | - | - | - | - | - |
| 1976 | - | - | - | - | - | - | - | - |
| 1977 | - | - | - | - | - | - | - | - |
| 1978 | - | - | - | - | - | - | - | - |
| 1979 | - | - | - | - | - | - | - | - |
| 1980 | - | - | - | - | - | - | - | - |
| 1981 | - | - | - | - | - | - | - | - |
| 1982 | - | - | - | - | - | - | - | - |
| 1983 | 102 | 0 | 0.00 | - | - | - | - | - |