Details
Reactor Type | Pressurised Water Reactor (or PWR) |
---|---|
Model | Hualong One |
Owner | Cnnc Fujian Fuqing Nuclear Power Co., Ltd |
Operator | CNNC Fujian Fuqing Nuclear Power Co Ltd |
Timeline
Construction Start | Thursday, 7 May 2015 |
---|---|
First Criticality | Wednesday, 21 October 2020 |
First Grid Connection | Friday, 27 November 2020 |
Commercial Operation | Saturday, 30 January 2021 |
Specifications
Capacity Net | 1075 MWe |
---|---|
Capacity Gross | 1161 MWe |
Thermal Capacity | 3050 MWt |
Design Net Capacity | 1075 MWe |
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Operational History
Electricity Supplied (GWh)
Energy Availability Factor (%)
Total Electricity Supplied (GWh)
Reactor History
Year | Reference Unit Power (MWe) | Annual Time Online (Hours) | Electricity Supplied (GWh) | Operation Factor (%) | Energy Availability Annual (%) | Energy Availability Cumulative (%) | Load Factor Annual (%) | Load Factor Cumulative (%) |
---|---|---|---|---|---|---|---|---|
2020 | 1000 | 312 | 91.72 | - | - | - | - | - |
2021 | 1075 | 7965 | 8461.95 | 90.10 | 91.50 | 91.50 | 89.00 | 89.00 |
2022 | 1075 | 6441 | 6721.77 | 73.50 | 74.90 | 82.80 | 71.40 | 79.80 |
2023 | 1075 | 8094 | 8433.14 | 92.40 | 90.60 | 85.50 | 89.60 | 83.10 |