Details

Reactor Type Pressurised Water Reactor (or PWR)
Model CPR-1000
Owner Guangxi Fangchenggang Nuclear Power Company, Ltd.
Operator Guangxi Fangchenggang Nuclear Power Company, Ltd.

Timeline

Construction Start Thursday, 23 December 2010
First Criticality Wednesday, 29 June 2016
First Grid Connection Friday, 15 July 2016
Commercial Operation Saturday, 1 October 2016

Specifications

Capacity Net 1000 MWe
Capacity Gross 1086 MWe
Thermal Capacity 2905 MWt
Design Net Capacity 1000 MWe

Operational History

Electricity Supplied (GWh)

Energy Availability Factor (%)

Total Electricity Supplied (GWh)

Reactor History

Year Reference Unit Power (MWe) Annual Time Online (Hours) Electricity Supplied (GWh) Operation Factor (%) Energy Availability Annual (%) Energy Availability Cumulative (%) Load Factor Annual (%) Load Factor Cumulative (%)
2016 1000 3297 2648.30 88.20 100.00 100.00 91.10 91.10
2017 1000 6827 6569.07 77.90 80.30 84.20 75.00 78.20
2018 1000 7816 7655.73 89.20 99.80 91.20 87.40 82.30
2019 1000 7625 7579.32 87.00 92.10 91.50 86.50 83.60
2020 1000 7911 7901.00 90.10 92.00 91.60 90.00 85.10
2021 1000 8760 8888.26 100.00 100.00 93.20 101.50 88.20
2022 1000 8129 8168.69 92.80 93.00 93.20 93.20 89.00
2023 1000 8018 8044.34 91.50 90.80 92.80 91.80 89.40

Source: Operating details - IAEA PRIS


See Also

Nuclear Power in China

Related News

WNN articles on China
Subscribe to receive updates on news