Details
Reactor Type | Pressurised Water Reactor (or PWR) |
---|---|
Model | CPR-1000 |
Owner | Cnnc Fujian Fuqing Nuclear Power Co., Ltd |
Operator | CNNC Fujian Fuqing Nuclear Power Co Ltd |
Timeline
Construction Start | Saturday, 17 November 2012 |
---|---|
First Criticality | Sunday, 16 July 2017 |
First Grid Connection | Saturday, 29 July 2017 |
Commercial Operation | Sunday, 17 September 2017 |
Specifications
Capacity Net | 1000 MWe |
---|---|
Capacity Gross | 1089 MWe |
Thermal Capacity | 2905 MWt |
Design Net Capacity | 1000 MWe |
Operational History
Electricity Supplied (GWh)
Energy Availability Factor (%)
Total Electricity Supplied (GWh)
Reactor History
Year | Reference Unit Power (MWe) | Annual Time Online (Hours) | Electricity Supplied (GWh) | Operation Factor (%) | Energy Availability Annual (%) | Energy Availability Cumulative (%) | Load Factor Annual (%) | Load Factor Cumulative (%) |
---|---|---|---|---|---|---|---|---|
2017 | 1000 | 2544 | 2540.07 | 100.00 | 100.00 | 100.00 | 100.00 | 100.00 |
2018 | 1000 | 6890 | 6682.09 | 78.60 | 77.80 | 82.30 | 76.30 | 81.00 |
2019 | 1000 | 7215 | 6599.79 | 82.40 | 91.30 | 86.30 | 75.30 | 78.50 |
2020 | 1000 | 6953 | 6587.82 | 79.20 | 92.00 | 88.00 | 75.00 | 77.40 |
2021 | 1000 | 8407 | 8297.78 | 96.00 | 99.40 | 90.70 | 94.70 | 81.50 |
2022 | 1000 | 7904 | 7799.96 | 90.20 | 89.00 | 90.40 | 89.00 | 82.90 |
2023 | 1000 | 5729 | 5665.02 | 65.40 | 66.80 | 86.60 | 64.70 | 80.00 |