Details
Reactor Type | Pressurised Water Reactor (or PWR) |
---|---|
Model | OPR-1000 |
Owner | Korea Hydro And Nuclear Power Co. |
Operator | Korea Hydro And Nuclear Power Co. |
Timeline
Construction Start | Friday, 1 October 1999 |
---|---|
First Criticality | Friday, 28 November 2003 |
First Grid Connection | Thursday, 18 December 2003 |
Commercial Operation | Thursday, 29 July 2004 |
Specifications
Capacity Net | 998 MWe |
---|---|
Capacity Gross | 1049 MWe |
Thermal Capacity | 2825 MWt |
Design Net Capacity | 950 MWe |
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Operational History
Electricity Supplied (GWh)
Energy Availability Factor (%)
Total Electricity Supplied (GWh)
Reactor History
Year | Reference Unit Power (MWe) | Annual Time Online (Hours) | Electricity Supplied (GWh) | Operation Factor (%) | Energy Availability Annual (%) | Energy Availability Cumulative (%) | Load Factor Annual (%) | Load Factor Cumulative (%) |
---|---|---|---|---|---|---|---|---|
2003 | 1001 | 188 | 18.43 | - | - | - | - | - |
2004 | 960 | 4963 | 4415.65 | 97.90 | 97.90 | 97.90 | 101.40 | 101.40 |
2005 | 960 | 7409 | 7321.60 | 84.60 | 83.80 | 88.00 | 87.10 | 91.30 |
2006 | 994 | 7925 | 7882.81 | 90.50 | 90.60 | 89.10 | 90.50 | 91.00 |
2007 | 995 | 8115 | 8025.93 | 92.60 | 91.90 | 89.90 | 92.10 | 91.30 |
2008 | 1001 | 8784 | 8763.82 | 100.00 | 99.90 | 92.20 | 99.70 | 93.20 |
2009 | 1001 | 7988 | 7924.16 | 91.20 | 90.80 | 91.90 | 90.40 | 92.70 |
2010 | 997 | 8245 | 8160.25 | 94.10 | 93.20 | 92.10 | 93.40 | 92.80 |
2011 | 997 | 8106 | 8052.72 | 92.50 | 92.00 | 92.10 | 92.20 | 92.70 |
2012 | 998 | 8784 | 8773.91 | 100.00 | 99.90 | 93.00 | 100.10 | 93.60 |
2013 | 996 | 7544 | 7476.53 | 86.10 | 85.40 | 92.20 | 85.70 | 92.80 |
2014 | 998 | 7408 | 7349.72 | 84.60 | 84.00 | 91.40 | 84.10 | 91.90 |
2015 | 998 | 8742 | 8687.64 | 99.80 | 99.10 | 92.10 | 99.40 | 92.60 |
2016 | 998 | 6961 | 6877.61 | 79.20 | 78.40 | 91.00 | 78.40 | 91.40 |
2017 | 998 | 6707 | 6663.73 | 76.60 | 82.30 | 90.40 | 76.20 | 90.30 |
2018 | 998 | 7097 | 6962.42 | 81.00 | 79.60 | 89.60 | 79.60 | 89.60 |
2019 | 998 | 6575 | 6467.68 | 75.10 | 74.00 | 88.60 | 74.00 | 88.50 |
2020 | 998 | 8784 | 8750.36 | 100.00 | 99.80 | 89.30 | 99.80 | 89.20 |
2021 | 998 | 7478 | 7383.73 | 85.40 | 84.50 | 89.00 | 84.50 | 89.00 |
2022 | 998 | 6950 | 6809.01 | 79.30 | 78.50 | 88.40 | 77.90 | 88.40 |
2023 | 998 | 7488 | 7376.79 | 85.50 | 84.40 | 88.20 | 84.40 | 88.20 |