Details
| Reactor Type | Pressurized Water Reactor (or PWR) |
|---|---|
| Model | CPR-1000 |
| Owner | Liaoning Hongyanhe Nuclear Power Co Ltd |
| Operator | Liaoning Hongyanhe Nuclear Power Co Ltd |
Timeline
| Construction Start | Saturday, 18 August 2007 |
|---|---|
| First Criticality | Wednesday, 16 January 2013 |
| First Grid Connection | Sunday, 17 February 2013 |
| Commercial Operation | Thursday, 6 June 2013 |
Specifications
| Capacity Net | 1061 MWe |
|---|---|
| Capacity Gross | 1119 MWe |
| Thermal Capacity | 2905 MWt |
| Design Net Capacity | 1061 MWe |
Operational History
Electricity Supplied (GWh)
Energy Availability Factor (%)
Total Electricity Supplied (GWh)
Reactor History
| Year | Reference Unit Power (MWe) | Annual Time Online (Hours) | Electricity Supplied (GWh) | Operation Factor (%) | Energy Availability Annual (%) | Energy Availability Cumulative (%) | Load Factor Annual (%) | Load Factor Cumulative (%) |
|---|---|---|---|---|---|---|---|---|
| 2013 | 1061 | 7632 | 5683.38 | 100.00 | 98.60 | 98.60 | 102.40 | 102.40 |
| 2014 | 1061 | 6218 | 6093.20 | 71.00 | 68.40 | 79.60 | 65.60 | 79.20 |
| 2015 | 1061 | 7756 | 7369.75 | 88.50 | 87.80 | 82.70 | 79.30 | 79.20 |
| 2016 | 1061 | 6694 | 6066.04 | 76.20 | 86.60 | 83.80 | 65.10 | 75.30 |
| 2017 | 1061 | 7720 | 7304.12 | 88.10 | 87.90 | 84.70 | 78.60 | 76.00 |
| 2018 | 1061 | 8760 | 8797.86 | 100.00 | 98.60 | 87.20 | 94.70 | 79.30 |
| 2019 | 1061 | 7954 | 8077.71 | 90.80 | 88.50 | 87.40 | 86.90 | 80.50 |
| 2020 | 1061 | 8033 | 7903.95 | 91.40 | 89.60 | 87.70 | 84.80 | 81.10 |
| 2021 | 1061 | 8760 | 8980.89 | 100.00 | 98.20 | 88.90 | 96.60 | 82.90 |
| 2022 | 1061 | 7696 | 7605.00 | 87.80 | 90.60 | 89.10 | 81.80 | 82.80 |
| 2023 | 1061 | 7071 | 7084.46 | 80.70 | 78.70 | 88.10 | 76.20 | 82.10 |
| 2024 | 1061 | 7999 | 7843.80 | 91.10 | 94.00 | 88.60 | 84.20 | 82.30 |