Details
Reactor Type | Pressurised Water Reactor (or PWR) |
---|---|
Model | CPR-1000 |
Owner | Liaoning Hongyanhe Nuclear Power Co Ltd |
Operator | Liaoning Hongyanhe Nuclear Power Co Ltd |
Timeline
Construction Start | Friday, 28 March 2008 |
---|---|
First Criticality | Thursday, 24 October 2013 |
First Grid Connection | Saturday, 23 November 2013 |
Commercial Operation | Tuesday, 13 May 2014 |
Specifications
Capacity Net | 1061 MWe |
---|---|
Capacity Gross | 1119 MWe |
Thermal Capacity | 2905 MWt |
Design Net Capacity | 1061 MWe |
Operational History
Electricity Supplied (GWh)
Energy Availability Factor (%)
Total Electricity Supplied (GWh)
Reactor History
Year | Reference Unit Power (MWe) | Annual Time Online (Hours) | Electricity Supplied (GWh) | Operation Factor (%) | Energy Availability Annual (%) | Energy Availability Cumulative (%) | Load Factor Annual (%) | Load Factor Cumulative (%) |
---|---|---|---|---|---|---|---|---|
2013 | 1061 | 340 | 82.00 | - | - | - | - | - |
2014 | 1061 | 5053 | 4963.31 | 79.80 | 81.10 | 81.10 | 72.50 | 72.50 |
2015 | 1061 | 3925 | 3496.01 | 44.80 | 65.60 | 71.80 | 37.60 | 51.60 |
2016 | 1061 | 5542 | 5288.78 | 63.10 | 87.50 | 77.70 | 56.80 | 53.50 |
2017 | 1061 | 6250 | 5790.37 | 71.40 | 96.00 | 82.70 | 62.30 | 55.90 |
2018 | 1061 | 7723 | 7737.78 | 88.20 | 88.20 | 83.90 | 83.20 | 61.80 |
2019 | 1061 | 8056 | 8077.34 | 92.00 | 89.70 | 84.90 | 86.90 | 66.20 |
2020 | 1061 | 8018 | 7767.35 | 91.30 | 89.30 | 85.60 | 83.30 | 68.80 |
2021 | 1061 | 8027 | 8195.34 | 91.60 | 89.40 | 86.10 | 88.20 | 71.30 |
2022 | 1061 | 8760 | 8882.06 | 100.00 | 98.00 | 87.40 | 95.60 | 74.10 |
2023 | 1061 | 8140 | 8143.39 | 92.90 | 90.50 | 87.80 | 87.60 | 75.50 |