Details
| Reactor Type | Pressurized Water Reactor (or PWR) |
|---|---|
| Model | CPR-1000 |
| Owner | Liaoning Hongyanhe Nuclear Power Co Ltd |
| Operator | Liaoning Hongyanhe Nuclear Power Co Ltd |
Timeline
| Construction Start | Saturday, 7 March 2009 |
|---|---|
| First Criticality | Monday, 27 October 2014 |
| First Grid Connection | Monday, 23 March 2015 |
| Commercial Operation | Sunday, 16 August 2015 |
Specifications
| Capacity Net | 1061 MWe |
|---|---|
| Capacity Gross | 1119 MWe |
| Thermal Capacity | 2905 MWt |
| Design Net Capacity | 1061 MWe |
Operational History
Electricity Supplied (GWh)
Energy Availability Factor (%)
Total Electricity Supplied (GWh)
Reactor History
| Year | Reference Unit Power (MWe) | Annual Time Online (Hours) | Electricity Supplied (GWh) | Operation Factor (%) | Energy Availability Annual (%) | Energy Availability Cumulative (%) | Load Factor Annual (%) | Load Factor Cumulative (%) |
|---|---|---|---|---|---|---|---|---|
| 2015 | 1061 | 2835 | 2322.53 | 48.00 | 100.00 | 100.00 | 43.20 | 43.20 |
| 2016 | 1061 | 5764 | 5483.99 | 65.60 | 94.70 | 96.00 | 58.80 | 54.90 |
| 2017 | 1061 | 5975 | 5631.50 | 68.20 | 80.90 | 89.60 | 60.60 | 57.40 |
| 2018 | 1061 | 6697 | 6535.98 | 76.40 | 89.70 | 89.60 | 70.30 | 61.20 |
| 2019 | 1061 | 7481 | 7491.34 | 85.40 | 82.70 | 88.00 | 80.60 | 65.70 |
| 2020 | 1061 | 7116 | 6938.56 | 81.00 | 98.00 | 89.90 | 74.40 | 67.40 |
| 2021 | 1061 | 7670 | 7943.87 | 87.60 | 85.80 | 89.20 | 85.50 | 70.20 |
| 2022 | 1061 | 7472 | 7198.11 | 85.30 | 89.70 | 89.30 | 77.40 | 71.20 |
| 2023 | 1061 | 7996 | 8025.66 | 91.30 | 88.80 | 89.30 | 86.40 | 73.00 |
| 2024 | 1061 | 8093 | 7863.64 | 92.10 | 90.30 | 89.40 | 84.40 | 74.20 |