Details
Reactor Type | Pressurised Water Reactor (or PWR) |
---|---|
Model | ACPR-1000 |
Owner | Liaoning Hongyanhe Nuclear Power Co Ltd |
Operator | Liaoning Hongyanhe Nuclear Power Co Ltd |
Timeline
Construction Start | Friday, 24 July 2015 |
---|---|
First Criticality | Thursday, 21 April 2022 |
First Grid Connection | Monday, 2 May 2022 |
Commercial Operation | Thursday, 23 June 2022 |
Specifications
Capacity Net | 1061 MWe |
---|---|
Capacity Gross | 1119 MWe |
Thermal Capacity | 2905 MWt |
Design Net Capacity | 1061 MWe |
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Operational History
Electricity Supplied (GWh)
Energy Availability Factor (%)
Total Electricity Supplied (GWh)
Reactor History
Year | Reference Unit Power (MWe) | Annual Time Online (Hours) | Electricity Supplied (GWh) | Operation Factor (%) | Energy Availability Annual (%) | Energy Availability Cumulative (%) | Load Factor Annual (%) | Load Factor Cumulative (%) |
---|---|---|---|---|---|---|---|---|
2022 | 1061 | 5007 | 5000.45 | 88.50 | 97.80 | 97.80 | 81.80 | 81.80 |
2023 | 1061 | 7661 | 7701.66 | 87.40 | 85.60 | 89.70 | 82.90 | 82.50 |