Details
| Reactor Type | Pressurized Water Reactor (or PWR) |
|---|---|
| Model | CPR-1000 |
| Owner | Fujian Ningde Nuclear Power Company, Ltd. |
| Operator | Fujian Ningde Nuclear Power Company, Ltd. |
Timeline
| Construction Start | Wednesday, 12 November 2008 |
|---|---|
| First Criticality | Friday, 20 December 2013 |
| First Grid Connection | Saturday, 4 January 2014 |
| Commercial Operation | Sunday, 4 May 2014 |
Specifications
| Capacity Net | 1018 MWe |
|---|---|
| Capacity Gross | 1089 MWe |
| Thermal Capacity | 2905 MWt |
| Design Net Capacity | 1018 MWe |
Operational History
Electricity Supplied (GWh)
Energy Availability Factor (%)
Total Electricity Supplied (GWh)
Reactor History
| Year | Reference Unit Power (MWe) | Annual Time Online (Hours) | Electricity Supplied (GWh) | Operation Factor (%) | Energy Availability Annual (%) | Energy Availability Cumulative (%) | Load Factor Annual (%) | Load Factor Cumulative (%) |
|---|---|---|---|---|---|---|---|---|
| 2014 | 1018 | 7044 | 6568.05 | 100.00 | 99.80 | 99.80 | 97.60 | 97.60 |
| 2015 | 1018 | 7145 | 6528.23 | 81.60 | 80.60 | 88.30 | 73.20 | 83.00 |
| 2016 | 1018 | 6290 | 5714.85 | 71.60 | 86.20 | 87.50 | 63.90 | 75.80 |
| 2017 | 1018 | 8371 | 8252.86 | 95.60 | 98.70 | 90.60 | 92.50 | 80.40 |
| 2018 | 1018 | 7938 | 7953.87 | 90.60 | 89.00 | 90.20 | 89.20 | 82.30 |
| 2019 | 1018 | 8026 | 8079.09 | 91.60 | 90.60 | 90.30 | 90.60 | 83.70 |
| 2020 | 1018 | 8784 | 8940.50 | 100.00 | 100.00 | 91.80 | 100.00 | 86.20 |
| 2021 | 1018 | 7904 | 8043.49 | 90.20 | 90.20 | 91.60 | 90.20 | 86.70 |
| 2022 | 1018 | 8158 | 8303.72 | 93.10 | 93.10 | 91.70 | 93.10 | 87.40 |
| 2023 | 1018 | 8718 | 8874.52 | 99.50 | 99.50 | 92.50 | 99.50 | 88.70 |
| 2024 | 1018 | 7428 | 7514.99 | 84.60 | 84.00 | 91.70 | 84.00 | 88.20 |