Details
Reactor Type | Pressurised Water Reactor (or PWR) |
---|---|
Model | CPR-1000 |
Owner | Fujian Ningde Nuclear Power Company, Ltd. |
Operator | Fujian Ningde Nuclear Power Company, Ltd. |
Timeline
Construction Start | Wednesday, 29 September 2010 |
---|---|
First Criticality | Wednesday, 16 March 2016 |
First Grid Connection | Tuesday, 29 March 2016 |
Commercial Operation | Thursday, 21 July 2016 |
Specifications
Capacity Net | 1018 MWe |
---|---|
Capacity Gross | 1089 MWe |
Thermal Capacity | 2905 MWt |
Design Net Capacity | 1018 MWe |
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Operational History
Electricity Supplied (GWh)
Energy Availability Factor (%)
Total Electricity Supplied (GWh)
Reactor History
Year | Reference Unit Power (MWe) | Annual Time Online (Hours) | Electricity Supplied (GWh) | Operation Factor (%) | Energy Availability Annual (%) | Energy Availability Cumulative (%) | Load Factor Annual (%) | Load Factor Cumulative (%) |
---|---|---|---|---|---|---|---|---|
2016 | 1018 | 3786 | 3694.87 | 95.90 | 99.90 | 99.90 | 91.80 | 91.80 |
2017 | 1018 | 5739 | 5303.77 | 65.50 | 84.30 | 88.90 | 59.50 | 69.00 |
2018 | 1018 | 8760 | 8917.08 | 100.00 | 100.00 | 93.50 | 100.00 | 81.80 |
2019 | 1018 | 7992 | 8074.33 | 91.20 | 90.50 | 92.60 | 90.50 | 84.40 |
2020 | 1018 | 8033 | 7998.17 | 91.40 | 89.40 | 91.90 | 89.40 | 85.50 |
2021 | 1018 | 8760 | 8916.45 | 100.00 | 100.00 | 93.40 | 100.00 | 88.20 |
2022 | 1018 | 7984 | 8126.58 | 91.10 | 91.10 | 93.00 | 91.10 | 88.60 |
2023 | 1018 | 7914 | 7967.67 | 90.30 | 89.40 | 92.60 | 89.40 | 88.70 |