Details
Reactor Type | Pressurised Water Reactor (or PWR) |
---|---|
Model | VVER V-320 |
Owner | Joint Stock Company 'Concern Rosenergoatom' |
Operator | Joint Stock Company 'Concern Rosenergoatom' |
Timeline
Construction Start | Tuesday, 1 September 1981 |
---|---|
First Criticality | Friday, 23 February 2001 |
First Grid Connection | Friday, 30 March 2001 |
Commercial Operation | Tuesday, 25 December 2001 |
Specifications
Capacity Net | 989 MWe |
---|---|
Capacity Gross | 1041 MWe |
Thermal Capacity | 3200 MWt |
Design Net Capacity | 950 MWe |
Operational History
Electricity Supplied (GWh)
Energy Availability Factor (%)
Total Electricity Supplied (GWh)
Reactor History
Year | Reference Unit Power (MWe) | Annual Time Online (Hours) | Electricity Supplied (GWh) | Operation Factor (%) | Energy Availability Annual (%) | Energy Availability Cumulative (%) | Load Factor Annual (%) | Load Factor Cumulative (%) |
---|---|---|---|---|---|---|---|---|
2001 | - | - | - | - | - | - | - | - |
2002 | 950 | 7543 | 7176.18 | 86.10 | 84.10 | 84.10 | 86.20 | 86.20 |
2003 | 950 | 7154 | 6973.93 | 81.70 | 81.30 | 82.70 | 83.80 | 85.00 |
2004 | 950 | 7766 | 7439.31 | 88.40 | 87.80 | 84.40 | 89.20 | 86.40 |
2005 | 950 | 7628 | 7232.86 | 87.10 | 85.80 | 84.80 | 86.90 | 86.50 |
2006 | 950 | 7386 | 7216.42 | 84.30 | 83.80 | 84.60 | 86.70 | 86.60 |
2007 | 950 | 7536 | 7309.44 | 86.00 | 85.30 | 84.70 | 87.80 | 86.80 |
2008 | 950 | 7799 | 7745.73 | 88.80 | 88.50 | 85.20 | 92.80 | 87.60 |
2009 | 950 | 7916 | 7927.02 | 90.40 | 90.30 | 85.90 | 95.20 | 88.60 |
2010 | 950 | 7828 | 7398.47 | 89.40 | 88.60 | 86.20 | 88.90 | 88.60 |
2011 | 950 | 7736 | 7695.35 | 88.30 | 88.20 | 86.40 | 92.50 | 89.00 |
2012 | 950 | 7614 | 7569.03 | 86.70 | 86.40 | 86.40 | 90.70 | 89.20 |
2013 | 950 | 8618 | 8557.12 | 98.40 | 98.20 | 87.40 | 102.80 | 90.30 |
2014 | 950 | 7498 | 7227.67 | 85.60 | 85.10 | 87.20 | 86.80 | 90.00 |
2015 | 950 | 6980 | 6713.50 | 79.70 | 76.80 | 86.40 | 80.70 | 89.40 |
2016 | 950 | 8753 | 8833.60 | 99.60 | 99.60 | 87.30 | 105.90 | 90.50 |
2017 | 950 | 7825 | 7840.38 | 89.30 | 89.20 | 87.40 | 94.20 | 90.70 |
2018 | 950 | 7719 | 7609.90 | 88.10 | 87.70 | 87.50 | 91.40 | 90.80 |
2019 | 950 | 8723 | 8620.25 | 99.60 | 99.50 | 88.10 | 103.60 | 91.50 |
2020 | 950 | 7689 | 7443.25 | 87.50 | 86.60 | 88.00 | 89.20 | 91.30 |
2021 | 989 | 7622 | 7416.99 | 87.00 | 85.70 | 87.90 | 85.60 | 91.00 |
2022 | 989 | 8728 | 8753.70 | 99.60 | 98.90 | 88.50 | 101.00 | 91.50 |
2023 | 989 | 7011 | 6993.42 | 80.00 | 79.30 | 88.00 | 80.70 | 91.00 |