Details
Reactor Type | Pressurised Water Reactor (or PWR) |
---|---|
Model | VVER V-428 |
Owner | Jiangsu Nuclear Power Corporation |
Operator | Jiangsu Nuclear Power Corporation |
Timeline
Construction Start | Wednesday, 20 September 2000 |
---|---|
First Criticality | Tuesday, 1 May 2007 |
First Grid Connection | Monday, 14 May 2007 |
Commercial Operation | Thursday, 16 August 2007 |
Specifications
Capacity Net | 1000 MWe |
---|---|
Capacity Gross | 1060 MWe |
Thermal Capacity | 3000 MWt |
Design Net Capacity | 990 MWe |
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Operational History
Electricity Supplied (GWh)
Energy Availability Factor (%)
Total Electricity Supplied (GWh)
Reactor History
Year | Reference Unit Power (MWe) | Annual Time Online (Hours) | Electricity Supplied (GWh) | Operation Factor (%) | Energy Availability Annual (%) | Energy Availability Cumulative (%) | Load Factor Annual (%) | Load Factor Cumulative (%) |
---|---|---|---|---|---|---|---|---|
2007 | 933 | 4471 | 3974.00 | 100.00 | 100.00 | 100.00 | 105.10 | 105.10 |
2008 | 933 | 7193 | 7003.03 | 81.90 | 81.20 | 85.90 | 85.40 | 90.40 |
2009 | 933 | 7054 | 6943.40 | 80.50 | 80.70 | 83.70 | 85.00 | 88.00 |
2010 | 933 | 7260 | 7131.13 | 82.90 | 82.30 | 83.20 | 87.20 | 87.80 |
2011 | 990 | 7658 | 7546.20 | 87.40 | 87.00 | 84.20 | 87.00 | 87.60 |
2012 | 990 | 7722 | 7640.12 | 87.90 | 87.80 | 84.90 | 87.90 | 87.70 |
2013 | 990 | 7837 | 7741.45 | 89.50 | 89.10 | 85.60 | 89.30 | 87.90 |
2014 | 990 | 7950 | 7901.45 | 90.80 | 91.10 | 86.30 | 91.10 | 88.40 |
2015 | 990 | 7790 | 7666.57 | 88.90 | 88.20 | 86.60 | 88.40 | 88.40 |
2016 | 990 | 7705 | 7326.45 | 87.70 | 87.40 | 86.70 | 84.20 | 87.90 |
2017 | 990 | 8430 | 8201.96 | 96.20 | 99.00 | 87.90 | 94.60 | 88.60 |
2018 | 990 | 8007 | 7661.18 | 91.40 | 91.60 | 88.20 | 88.30 | 88.60 |
2019 | 990 | 7833 | 7644.10 | 89.40 | 91.10 | 88.40 | 88.10 | 88.50 |
2020 | 990 | 8683 | 7991.08 | 98.80 | 98.30 | 89.20 | 91.90 | 88.80 |
2021 | 1000 | 8253 | 7972.07 | 94.20 | 92.30 | 89.40 | 91.00 | 88.90 |
2022 | 1000 | 7861 | 7420.49 | 89.70 | 90.50 | 89.50 | 84.70 | 88.70 |
2023 | 1000 | 8760 | 8015.09 | 100.00 | 99.70 | 90.10 | 91.50 | 88.80 |