Details
Reactor Type | Pressurised Water Reactor (or PWR) |
---|---|
Model | VVER V-428M |
Owner | Jiangsu Nuclear Power Corporation |
Operator | Jiangsu Nuclear Power Corporation |
Timeline
Construction Start | Friday, 27 September 2013 |
---|---|
First Criticality | Sunday, 30 September 2018 |
First Grid Connection | Saturday, 27 October 2018 |
Commercial Operation | Saturday, 22 December 2018 |
Specifications
Capacity Net | 1060 MWe |
---|---|
Capacity Gross | 1126 MWe |
Thermal Capacity | 3000 MWt |
Design Net Capacity | 1060 MWe |
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Operational History
Electricity Supplied (GWh)
Energy Availability Factor (%)
Total Electricity Supplied (GWh)
Reactor History
Year | Reference Unit Power (MWe) | Annual Time Online (Hours) | Electricity Supplied (GWh) | Operation Factor (%) | Energy Availability Annual (%) | Energy Availability Cumulative (%) | Load Factor Annual (%) | Load Factor Cumulative (%) |
---|---|---|---|---|---|---|---|---|
2018 | 1045 | 1035 | 732.62 | - | - | - | - | - |
2019 | 1045 | 7462 | 7519.47 | 85.20 | 84.60 | 84.60 | 82.10 | 82.10 |
2020 | 1045 | 7003 | 7033.68 | 79.70 | 95.20 | 89.90 | 76.60 | 79.40 |
2021 | 1060 | 8422 | 8610.04 | 96.10 | 95.90 | 91.90 | 92.70 | 83.90 |
2022 | 1060 | 8244 | 8273.71 | 94.10 | 93.20 | 92.20 | 89.10 | 85.20 |
2023 | 1060 | 7932 | 7630.39 | 90.60 | 92.40 | 92.20 | 82.20 | 84.60 |