Reactor Type | Pressurised Water Reactor (or PWR) |
---|---|
Model | ACPR-1000 |
Owner | Jiangsu Nuclear Power Corporation |
Operator | Jiangsu Nuclear Power Corporation |
Timeline
Construction Start | Sunday, 27 December 2015 |
---|---|
First Criticality | Monday, 27 July 2020 |
First Grid Connection | Saturday, 8 August 2020 |
Commercial Operation | Tuesday, 8 September 2020 |
Specifications
Capacity Net | 1060 MWe |
---|---|
Capacity Gross | 1118 MWe |
Thermal Capacity | 2905 MWt |
Design Net Capacity | 1000 MWe |
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Operational History
Electricity Supplied (GWh)
Energy Availability Factor (%)
Total Electricity Supplied (GWh)
Reactor History
Year | Reference Unit Power (MWe) | Annual Time Online (Hours) | Electricity Supplied (GWh) | Operation Factor (%) | Energy Availability Annual (%) | Energy Availability Cumulative (%) | Load Factor Annual (%) | Load Factor Cumulative (%) |
---|---|---|---|---|---|---|---|---|
2020 | 1000 | 3383 | 2901.91 | 95.90 | 93.30 | 93.30 | 91.30 | 91.30 |
2021 | 1060 | 7400 | 7538.34 | 84.50 | 84.40 | 86.50 | 81.20 | 83.60 |
2022 | 1060 | 8760 | 8933.22 | 100.00 | 98.40 | 91.60 | 96.20 | 89.00 |
2023 | 1060 | 7864 | 8038.07 | 89.80 | 91.50 | 91.60 | 86.60 | 88.30 |