Details
| Reactor Type | Pressurized Water Reactor (or PWR) |
|---|---|
| Model | ACPR-1000 |
| Owner | Yangjiang Nuclear Power Company |
| Operator | Yangjiang Nuclear Power Company |
Timeline
| Construction Start | Wednesday, 18 September 2013 |
|---|---|
| First Criticality | Wednesday, 16 May 2018 |
| First Grid Connection | Wednesday, 23 May 2018 |
| Commercial Operation | Thursday, 12 July 2018 |
Specifications
| Capacity Net | 1000 MWe |
|---|---|
| Capacity Gross | 1086 MWe |
| Thermal Capacity | 2905 MWt |
| Design Net Capacity | 1021 MWe |
Operational History
Electricity Supplied (GWh)
Energy Availability Factor (%)
Total Electricity Supplied (GWh)
Reactor History
| Year | Reference Unit Power (MWe) | Annual Time Online (Hours) | Electricity Supplied (GWh) | Operation Factor (%) | Energy Availability Annual (%) | Energy Availability Cumulative (%) | Load Factor Annual (%) | Load Factor Cumulative (%) |
|---|---|---|---|---|---|---|---|---|
| 2018 | 1000 | 4847 | 4365.35 | 97.30 | 99.10 | 99.10 | 94.40 | 94.40 |
| 2019 | 1000 | 6927 | 6699.42 | 79.10 | 82.40 | 88.00 | 76.50 | 82.50 |
| 2020 | 1000 | 7706 | 7318.68 | 87.70 | 94.60 | 90.60 | 83.30 | 82.80 |
| 2021 | 1000 | 8314 | 8195.95 | 94.90 | 94.40 | 91.70 | 93.60 | 85.90 |
| 2022 | 1000 | 8177 | 8236.09 | 93.30 | 92.70 | 91.90 | 94.00 | 87.70 |
| 2023 | 1000 | 8088 | 7988.19 | 92.30 | 92.20 | 92.00 | 91.20 | 88.30 |
| 2024 | 1000 | 8784 | 8982.32 | 100.00 | 100.00 | 93.20 | 102.30 | 90.50 |