Details

Reactor Type Pressurised Water Reactor (or PWR)
Model VVER V-320
Owner Joint Stock Company 'Concern Rosenergoatom'
Operator Joint Stock Company 'Concern Rosenergoatom'

Timeline

Construction Start Tuesday, 1 October 1985
First Criticality Thursday, 25 November 2004
First Grid Connection Thursday, 16 December 2004
Commercial Operation Tuesday, 8 November 2005

Specifications

Capacity Net 950 MWe
Capacity Gross 1000 MWe
Thermal Capacity 3200 MWt
Design Net Capacity 950 MWe

Operational History

Electricity Supplied (GWh)

Energy Availability Factor (%)

Total Electricity Supplied (GWh)

Reactor History

Year Reference Unit Power (MWe) Annual Time Online (Hours) Electricity Supplied (GWh) Operation Factor (%) Energy Availability Annual (%) Energy Availability Cumulative (%) Load Factor Annual (%) Load Factor Cumulative (%)
2004 950 360 5.20 - - - - -
2005 950 5686 4345.70 100.00 100.00 100.00 100.80 100.80
2006 950 6692 6287.23 76.40 74.90 78.50 75.60 79.20
2007 950 7505 7185.22 85.70 85.00 81.50 86.30 82.50
2008 950 7737 7561.73 88.10 87.70 83.50 90.60 85.00
2009 950 7553 6806.52 86.20 86.00 84.10 81.80 84.30
2010 950 7248 6902.21 82.70 82.10 83.70 82.90 84.00
2011 950 7427 7088.32 84.80 84.80 83.90 85.20 84.20
2012 950 8091 7765.07 92.10 91.80 85.00 93.00 85.40
2013 950 6698 6505.71 76.50 76.20 83.90 78.20 84.60
2014 950 6918 6599.48 79.00 78.30 83.30 79.30 84.00
2015 950 8196 7665.20 93.60 92.30 84.20 92.10 84.80
2016 950 5612 5233.15 63.90 62.40 82.20 62.70 82.80
2017 950 7990 7892.37 91.20 91.10 83.00 94.80 83.80
2018 950 7558 7504.45 86.30 85.80 83.20 90.20 84.30
2019 950 7362 7322.22 84.00 83.70 83.20 88.00 84.50
2020 950 8784 8807.69 100.00 100.00 84.30 105.60 85.90
2021 950 7369 7321.24 84.10 83.70 84.30 88.00 86.00
2022 950 6929 6877.28 79.10 78.90 84.00 82.60 85.80
2023 950 8760 8833.38 100.00 100.00 84.80 106.10 87.00

Source: Operating details - IAEA PRIS