Details

Reactor Type Pressurised Water Reactor (or PWR)
Model EPR
Owner Teollisuuden Voima Oyj
Operator Teollisuuden Voima Oyj

Timeline

Construction Start Friday, 12 August 2005
First Criticality Tuesday, 21 December 2021
First Grid Connection Saturday, 12 March 2022
Commercial Operation Sunday, 16 April 2023

Specifications

Capacity Net 1600 MWe
Capacity Gross 1660 MWe
Thermal Capacity 4300 MWt
Design Net Capacity 1600 MWe

Operational History

Electricity Supplied (GWh)

Energy Availability Factor (%)

Total Electricity Supplied (GWh)

Reactor History

Year Reference Unit Power (MWe) Annual Time Online (Hours) Electricity Supplied (GWh) Operation Factor (%) Energy Availability Annual (%) Energy Availability Cumulative (%) Load Factor Annual (%) Load Factor Cumulative (%)
2022 1600 2145 1886.77 - - - - -
2023 1600 7156 10371.84 98.60 96.30 96.30 88.80 88.80

Source: Operating details - IAEA PRIS