Details
| Reactor Type | Pressurized Water Reactor (or PWR) |
|---|---|
| Model | APR-1400 |
| Owner | Korea Hydro And Nuclear Power Co. |
| Operator | Korea Hydro And Nuclear Power Co. |
Timeline
| Construction Start | Wednesday, 19 June 2013 |
|---|---|
| First Criticality | Wednesday, 6 December 2023 |
| First Grid Connection | Thursday, 21 December 2023 |
| Commercial Operation | Friday, 5 April 2024 |
Specifications
| Capacity Net | 1416 MWe |
|---|---|
| Capacity Gross | 1455 MWe |
| Thermal Capacity | 3983 MWt |
| Design Net Capacity | 1340 MWe |
Operational History
Electricity Supplied (GWh)
Energy Availability Factor (%)
Total Electricity Supplied (GWh)
Reactor History
| Year | Reference Unit Power (MWe) | Annual Time Online (Hours) | Electricity Supplied (GWh) | Operation Factor (%) | Energy Availability Annual (%) | Energy Availability Cumulative (%) | Load Factor Annual (%) | Load Factor Cumulative (%) |
|---|---|---|---|---|---|---|---|---|
| 2023 | - | - | - | - | - | - | - | - |
| 2024 | 1416 | 7430 | 10097.64 | 94.40 | 94.50 | 94.50 | 94.90 | 94.90 |