Nuclear Reactors in Belgium

2
Operable
Reactors
2,056 MWe
42%
Nuclear Share
of Generation
29,732 GWh (2024)
0
Reactors Under
Construction
0 MWe

Total Operable Nuclear Capacity

Total Electricity Generated

All Operable Reactors

Reactor Name Model Process Capacity (MWe) Grid Connection Load Factor (2024) (%) Electricity Generated (2024) (GWh)
Doel 4 W (3-loop) PWR 1026 08/04/1985 72.00 6492.93
Tihange 3 W (3-loop) PWR 1030 15/06/1985 98.10 8874.52

All Permanent Shutdown Reactors

Reactor Name Model Process Net Capacity (MWe) Permanent Shutdown
BR-3 Prototype PWR 10 30/06/1987
Doel 1 W (2-loop) PWR 445 14/02/2025
Doel 2 W (2-loop) PWR 445 30/11/2025
Doel 3 W (3-loop) PWR 1006 23/09/2022
Tihange 1 Framatome 3 loops reactor PWR 962 30/09/2025
Tihange 2 W (3-loop) PWR 1008 31/01/2023