Ghana - World Nuclear Outlook Report

Nuclear policy and outlook

Ghana has had aspirations to develop nuclear energy since the 1960s and currently has a target of about 1000 MWe of nuclear capacity operational by 2034. In September 2023, Nuclear Power Ghana (NPG) announced that it selected Nsuban in Ghana’s Western Region as its preferred nuclear power plant location, with Obotan in the Central Region as a backup site.

Ghana signed a framework agreement with China National Nuclear Corporation (CNNC) in April 2024 to develop an HPR1000 (Hualong One) nuclear power plant. In August 2024, Nuclear Power Ghana (NPG) signed a two-year framework agreement with US developer and financier Regnum Technology Group for a NuScale VOYGR-12 multi-module SMR plant, targeting commercial operation in the mid-2030s.

In March 2025, NPG announced that CNNC had been selected to develop an approximately 1200 MWe reactor under a build-operate-transfer model, alongside the NuScale SMR project. In early 2026, NPG reported that insufficient funding was delaying detailed site characterization and environmental impact studies.

Table Gh.1 Contributions to total capacity projection in 2050 (gross)

60 year operation (MWe) 80 year operation (MWe) Currently under construction capacity (MWe) Planned capacity (MWe) Proposed capacity (MWe) Potential capacity (MWe) Government capacity target (MWe) Additional capacity* required to meet government target (MWe) Total capacity (MWe)
- - - - - - 1000 0 1000
*Capacity additional to operable, under construction, planned, proposed and potential capacities required to meet the government target.
 

Readiness Assessment

Ghana has a sustained commitment to introducing nuclear power, an established programme organization, a dedicated regulator and an emerging owner–operator.Preferred sites have been identified and partnerships established for both a large reactor and small modular reactors.

Country Category Candidate
Policy Framework Readiness Low-Moderate
Durable political commitment, a 1000 MWe objective, owner/operator structure, vendor agreements and site programme are established, but final project and financing decisions remain outstanding
Institutional & Infrastructure Readiness Low-Moderate
Independent regulator, nuclear research capability and international training provide a sound base; power reactor licensing and project delivery remain untested.
Programme & Project Development Readiness Low-Moderate
Preferred site and two technology/vendor tracks are identifiable, but a funding shortfall has prevented these projects from reaching final contract, financing, or licencing stages.
Target Achievability Low-Moderate
Nuclear deployment remains credible, but the target of approximately 1000 MWe by 2034 is unlikely to be met.