Uzbekistan - World Nuclear Outlook Report

Nuclear policy and outlook

During a May 2024 state visit to Uzbekistan by Russian President Vladimir Putin, a contract was signed for Rosatom to construct a six-unit small modular reactor plant in the Jizzakh region, based on the 55 MWe RITM-200N. In September 2025 an agreement was signed confirming that the Jizzakh project would now consist of two VVER-1000 units and two RITM-200N units, together with key terms for future fuel supply contracts. Excavation for the first RITM-200N reactor building began in October 2025 and a nuclear site licence was granted in March 2026.

In June 2026 the Committee for Industrial, Radiation and Nuclear Safety issued a construction licence for the first RITM-200N unit, which is scheduled to reach criticality in late 2029. The two VVER-1000 units are planned to follow in about 2033 and 2035.

Table Uz.2 Contributions to total capacity projection in 2050 (gross)

60 year operation (MWe) 80 year operation (MWe) Currently under construction capacity (MWe) Planned capacity (MWe) Proposed capacity (MWe) Potential capacity (MWe) Government capacity target (MWe) Additional capacity* required to meet government target (MWe) Total capacity (MWe)
0 0 0 2110 - - - - 2110
*Capacity additional to operable, under construction, planned, proposed and potential capacities required to meet the government target.
 

Readiness Assessment

Uzbekistan has strong political backing and its first SMR is about to start construction, but the country has no experience of licensing or operating power reactors.

Country Category Newcomer
Policy Framework Readiness High
Government commitment has moved through legislation, contract, site, public consultation and an enlarged first plant configuration.
Institutional & Infrastructure Readiness Moderate-High
Uzbekistan has a dedicated programme agency, independent regulatory body, but no commercial power reactor operating experience.
Programme & Project Development High
Construction of the first RITM-200N unit was approved in June 2026 and site work has commenced.
Target Achievability Moderate-High
The complete 2110 GWe project is now agreed and preliminary construction has begun, although the 2029-35 deadlines are demanding. In addition, although a financial framework in place, full project financing is still in progress.