Bangladesh - World Nuclear Performance Report

Bangladesh operable reactors, share of generation, under construction

Two VVER-1200 units are under construction in Bangladesh at Rooppur, on the east bank of the Padma River, about 160 km northwest of Dhaka.

Construction of unit 1 began in November 2017, followed by unit 2 in July 2018. The reactors are designated as V-523, which are based on the V-392M reactors at Novovoronezh II in Russia. Once completed, the two-unit plant is expected to provide about 9% of the country’s electricity. In October 2023 Bangladesh received its first delivery of nuclear fuel, marking the point when the Rooppur site became a nuclear facility.

Earlier, in October 2022 the government announced that the construction of Rooppur was running approximately one year behind schedule due to issues stemming from the COVID-19 pandemic and Russia’s invasion of Ukraine. Unit 1 is now expected to start providing electricity to Bangladesh’s national grid in 2026. In March 2025 hydraulic tests were completed, and the turbine was
installed at Rooppur 1.

World Nuclear News
IAEA mission sees Rooppur 1 safety commitment
Thursday, 28 August 2025
The operator of the Rooppur nuclear power plant in Bangladesh is committed to taking all steps to en...
Rooppur unit 1 progressesing though commissioning tests
Tuesday, 5 August 2025
A blowdown of the fresh steam pipelines in the turbine compartment has been completed at the first u...
Rooppur 1 hot testing under way
Thursday, 17 July 2025
The first nuclear power unit at the Rooppur nuclear power plant in Bangladesh is undergoing hot test...