Details

Reactor Type Pressurized Heavy Water Reactor (or PHWR)
Model CANDU 6
Owner Energie NB Power
Operator Energie NB Power

Timeline

Construction Start Thursday, 1 May 1975
First Criticality Sunday, 25 July 1982
First Grid Connection Saturday, 11 September 1982
Commercial Operation Tuesday, 1 February 1983

Specifications

Capacity Net 660 MWe
Capacity Gross 705 MWe
Thermal Capacity 2180 MWt
Design Net Capacity 660 MWe

Operational History

Electricity Supplied (GWh)

Energy Availability Factor (%)

Total Electricity Supplied (GWh)

Reactor History

Year Reference Unit Power (MWe) Annual Time Online (Hours) Electricity Supplied (GWh) Operation Factor (%) Energy Availability Annual (%) Energy Availability Cumulative (%) Load Factor Annual (%) Load Factor Cumulative (%)
1982 635 0 691.00 - - - - -
1983 640 7875 4742.90 89.40 86.00 86.00 85.80 85.80
1984 635 7927 5000.94 90.20 88.90 87.60 89.70 87.80
1985 635 8547 5421.91 97.60 96.90 90.70 97.50 91.10
1986 635 8257 5223.09 94.30 93.40 91.40 93.90 91.80
1987 635 8110 5107.73 92.60 91.20 91.40 91.80 91.80
1988 635 8383 5338.25 95.40 94.80 92.00 95.70 92.50
1989 635 8271 5266.67 94.40 93.60 92.20 94.70 92.80
1990 635 8384 5333.71 95.70 94.70 92.50 95.90 93.20
1991 635 8500 5437.17 97.00 96.70 93.00 97.80 93.70
1992 635 7748 4829.78 88.20 85.80 92.30 86.60 93.00
1993 635 8391 5320.00 95.80 95.10 92.50 95.60 93.20
1994 635 8270 5230.10 94.40 93.50 92.60 94.00 93.30
1995 635 2615 1611.40 29.80 29.00 87.70 29.00 88.30
1996 635 7363 4587.83 83.80 81.40 87.20 82.20 87.90
1997 635 5564 3455.59 63.50 61.60 85.50 62.10 86.20
1998 635 6111 3782.35 69.80 66.00 84.30 68.00 85.00
1999 635 6797 4082.74 77.60 72.00 83.60 73.40 84.30
2000 635 6792 3966.85 77.30 70.50 82.80 71.10 83.60
2001 635 7418 4451.33 84.70 79.10 82.60 80.00 83.40
2002 635 6107 3760.64 69.70 67.60 81.90 67.60 82.60
2003 635 7869 4739.52 89.80 84.40 82.00 85.20 82.70
2004 635 7310 4299.74 83.20 82.60 82.00 77.10 82.50
2005 635 7632 4372.64 87.10 86.80 82.20 78.60 82.30
2006 635 7755 4361.99 88.50 88.70 82.50 78.40 82.20
2007 635 7511 4121.82 85.70 86.00 82.60 74.10 81.80
2008 635 2111 1150.56 24.00 24.00 80.40 20.60 79.50
2009 635 0 0.00 0.00 0.00 77.40 0.00 76.50
2010 635 0 0.00 0.00 0.00 74.60 0.00 73.80
2011 635 0 0.00 0.00 0.00 72.00 0.00 71.20
2012 660 966 411.48 11.00 7.50 69.90 7.30 69.10
2013 660 7879 4111.15 90.00 70.80 69.90 71.10 69.10
2014 660 7229 4724.62 82.50 81.90 70.30 81.70 69.50
2015 660 6993 4277.04 79.80 74.60 70.40 74.00 69.70
2016 660 6989 4548.99 79.60 78.20 70.70 78.50 70.00
2017 660 7928 5151.32 90.50 89.20 71.20 89.10 70.50
2018 660 7469 4894.15 85.30 84.50 71.60 84.60 70.90
2019 660 7663 5015.68 87.50 86.70 72.00 86.80 71.40
2020 660 7302 4801.00 83.10 82.50 72.30 82.80 71.70
2021 660 7038 4418.52 80.30 76.40 72.40 76.40 71.80
2022 660 5499 3546.75 62.80 61.30 72.10 61.40 71.50
2023 660 7366 4764.67 84.10 82.40 72.40 82.40 71.80

Source: Operating details - IAEA PRIS


See Also

Nuclear Power in Canada

Related News

WNN articles on Canada
Subscribe to receive updates on news