Details
Reactor Type | Pressurised Water Reactor (or PWR) |
---|---|
Model | APR-1400 |
Owner | Korea Hydro And Nuclear Power Co. |
Operator | Korea Hydro And Nuclear Power Co. |
Timeline
Construction Start | Wednesday, 19 June 2013 |
---|---|
First Criticality | Wednesday, 6 December 2023 |
First Grid Connection | Thursday, 21 December 2023 |
Commercial Operation | Friday, 5 April 2024 |
Specifications
Capacity Net | 1340 MWe |
---|---|
Capacity Gross | 1455 MWe |
Thermal Capacity | 3983 MWt |
Design Net Capacity | 1340 MWe |
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Sorry, we have no imagery here.
Operational History
Electricity Supplied (GWh)
Energy Availability Factor (%)
Total Electricity Supplied (GWh)
Reactor History
Year | Reference Unit Power (MWe) | Annual Time Online (Hours) | Electricity Supplied (GWh) | Operation Factor (%) | Energy Availability Annual (%) | Energy Availability Cumulative (%) | Load Factor Annual (%) | Load Factor Cumulative (%) |
---|---|---|---|---|---|---|---|---|
2023 | - | - | - | - | - | - | - | - |