Tomari 3 shut down on 5 May 2012 and is in the process of seeking clearance to restart, after the introduction of new regulatory requirements in 2013 by Japan's Nuclear Regulation Authority.

Details

Reactor Type Pressurised Water Reactor (or PWR)
Model M (3-loop)
Owner Hokkaido Electric Power Co., Inc.
Operator Hokkaido Electric Power Co., Inc.

Timeline

Construction Start Thursday, 18 November 2004
First Criticality Tuesday, 3 March 2009
First Grid Connection Friday, 20 March 2009
Commercial Operation Tuesday, 22 December 2009
Long-term Shutdown Saturday, 5 May 2012

Specifications

Capacity Net 866 MWe
Capacity Gross 912 MWe
Thermal Capacity 2660 MWt
Design Net Capacity 866 MWe

Operational History

Electricity Supplied (GWh)

Energy Availability Factor (%)

Total Electricity Supplied (GWh)

Reactor History

Year Reference Unit Power (MWe) Annual Time Online (Hours) Electricity Supplied (GWh) Operation Factor (%) Energy Availability Annual (%) Energy Availability Cumulative (%) Load Factor Annual (%) Load Factor Cumulative (%)
2009 866 3603 2426.85 - - - - -
2010 866 8760 7904.94 100.00 100.00 100.00 104.20 104.20
2011 866 7283 6556.84 83.10 82.90 91.40 86.40 95.30
2012 866 3023 2731.82 34.40 34.40 72.40 35.90 75.50
2013 866 0 0.00 0.00 0.00 54.30 0.00 56.60
2014 866 0 0.00 0.00 0.00 43.40 0.00 45.30
2015 866 0 0.00 0.00 0.00 36.20 0.00 37.80
2016 866 0 0.00 0.00 0.00 31.00 0.00 32.40
2017 866 0 0.00 0.00 0.00 27.20 0.00 28.30
2018 866 0 0.00 0.00 0.00 24.10 0.00 25.20
2019 866 0 0.00 0.00 0.00 21.70 0.00 22.60
2020 866 0 0.00 0.00 0.00 19.70 0.00 20.60
2021 866 0 0.00 0.00 0.00 18.10 0.00 18.90
2022 866 0 0.00 0.00 0.00 18.10 0.00 18.90
2023 866 0 0.00 0.00 0.00 18.10 0.00 18.90

Source: Operating details - IAEA PRIS